PERI Formwork Systems, Inc., Projects

PERI Systems In Use

MULTIPROP Slab prop

The Riverfront Venue in Cincinnati, Ohio

The Riverfront Venue in Cincinnati, Ohio

To form the Concession Stand walls, 12'' high x 8'' wide (3.66 x 2.44 m) RUNDFLEX gangs were shipped to the jobsite, where the 8'' high x 8'' wide (2.44 x 2.44 m) gangs, from the retaining walls, were then attached on top creating a form 20'' ...
Old Allegheny County Jail, Pittsburgh, PA

Old Allegheny County Jail, Pittsburgh, PA, USA

With time and space at a minimum and no possibility to use a crane, Mascaro needed light and easy to handle formwork systems that allowed cost-effective fulfilment of the contractual requirements.

Stuttgart Airport, New Terminal 3, Germany

Since the beginning of the nineties the annual number of air passengers has almost doubled to around 8 million in the capital of Baden-Wuerttemberg.��
Redondo Tech Center, Redondo Beach, CA

Redondo Tech Center, Redondo Beach, CA, USA

This 4-storey 8“ (0.20 m) and 12“ (0.30 m) flat slab construction will combine high tech office space with self storage and parking facilities after completion.
The Residence at the Ritz-Carlton, Miami, FL

The Residence at the Ritz-Carlton, Miami, FL, USA

Each of the 260'' (79.24 m) high buildings has 22 floors. The complex includes a hotel and a condominium.