|
Located along the Chicago River at the junction of Loop and North Michigan Avenue, the Trump International Hotel and Tower will be the latest skyscraper to rise above the Chicago skyline.
|
|
In order to produce the level of finish required for this building, Elite Formwork Inc. used the KG Climbing Bracket along with an extension for the finishing platform. Using this system allowed the contractor to perform the required finish ...
|
|
Elite Formwork Inc. decided to use the PERI UNIPORTAL table system. By using this system, tables ranging in size from 16 ft x 26 ft (4.80 m x 8.00 m) were effectively flown by using the self leveling C-Hook.
|
|
On this project, PERI supplied the SKYDECK slab formwork system, TRIO wall formwork and KG climbing brakkets.
|
|
PERI SKYDECK system uses a drophead technology which allows the shores to stay in place during the stripping procedure.
|