Hotel Poznan, Poznan, Poland



Built on climbing brackets

Facade scaffold to overcome poor substructure

For the renovation and insulation of the 51.00 m high hotel complex the erection of the facade scaffold was not possible off the low level roofs.

As a suspended scaffold was not possible the PERI engineers decided to use a series of PERI climbing brackets KG 180 and CB 160. These were cantilevered from the building facade and anchored back to the floor slabs to support the external scaffold. It was necessary to introduce two levels of brackets as the fabric of the building was not capable of withstanding the imposed loads.��

PERI Systems In Use
  • CB Climbing System
  • PERI UP T 70 / T 100 Frame scaffolding
  • Field Service: PERI Polska Sp. z o.o., Poland