Stoneway Concrete Silos, Renton, WA, USA



Fast Learning Curve with PERI RUNDFLEX

In Renton, WA Gary Merlino Construction built a new batch plant for Stoneway Concrete. Several concrete silos with a total height of 48'' (14.63 m) and a wall thickness of 12"-18" (0.30 - 0.46 m) were built in seven months.

Merlino Construction decided to cast these silos in place, as this method would save them time and cost versus slip forming. Because of the safety by PERI''s KG system, they decided to go with PERI.

In addition to KG 180 and 240 (24 panels in total), PERI also supplied its RUNDFLEX, SKYDECK and TRIO systems, the latter being used on adjoining tunnels.

PERI Systems In Use
  • RUNDFLEX Circular Wall Formwork
  • SKYDECK Aluminum Slab Formwork System
  • TRIO
  • Contractor: Gary Merlino Construction, Seattle, WA
    Field Service: PERI USA, Northwest