PERI Formwork Systems, Inc., Projects - Creve Coeur Lake Memorial Park Bridge, St.Louis, MO, USA PERI Formwork Systems, Inc., Projects - Creve Coeur Lake Memorial Park Bridge, St.Louis, MO, USA PERI Formwork Systems, Inc., Projects - Creve Coeur Lake Memorial Park Bridge, St.Louis, MO, USA More Images  

Creve Coeur Lake Memorial Park Bridge, St.Louis, MO, USA



Labor Savings achieved on complicated Bridge Project

The State of Missouri constructed this $72 million bridge project as part of the extension of State Rte. 364 (Page Ave.) in Maryland Heights, MO. The approximately half-mile long, nine-span, ten-lane bridge spans the southern tip of Creve Coeur Lake.

The bridge is built cast-in-place in a double box section design with a total width of 85 ft (26.05 m). Walter Construction was faced with the task of finding a formwork system that could solve the complicated requirements of this project with a simple approach reducing labor costs.

This is why they chose to go with PERI. PERI´s economical solution enabled Walter to keep their schedule with a minimum of labor. After the first of two pier tables had been completed, the construction time on the subsequent pier tables was further reduced.

PERI Systems In Use
  • MULTIPROP System
  • TRIO
  • Contractor: Walter Construction (USA), Inc., St.Louis, MO
    Field Service: PERI USA, Indianapolis and PERI Germany, Weissenhorn