Great Wolf Lodge, Grapevine, Texas
110,000 ft² (10,219 m²) of SKYDECK
gets project Back on Schedule
The concrete work on this 8 story, $100 million resort project began in September 2006. Pour sizes are typically 500 yd³ to 700 yd³ (382 m³ to 535 m³) each and the 70,000 ft² (6,690 m²) slab is typically split into two separate pours. The concrete construction began almost two weeks behind schedule and the labor crew had never worked with SKYDECK before. PERI delivered over 110,000 ft² (10,220 m²) of SKYDECK to the customer on 2 days notice to get the concrete project back on track.
|
| PERI Systems In Use |
SKYDECK Aluminum Slab Formwork System
|
|
Billy Cantrell
Project Superintendent
“With the project starting late, we have managed to get back on schedule thanks to SKYDECK. This was impressive considering that our workers had never used the system before.”
|
|
| General Contractor: |
Turner Construction Company |
| Contractor: |
Urban Concrete Contractors Ltd., San Antonio, TX |
|
Field Service:
|
PERI Formwork Systems, Inc., United States of America
|
|
PERI Scope 01.2007
|
|