SAK used SKYDECK, the modular aluminum panel slab system for the deck of this building in order to meet a 10 day floor cycle.
|
|
Concrete Structures worked with PERI to shore a large 70,000 ft² (6,500 m²) main level deck that will later support the steel structure of the numerous overlying residential and commercial buildings.
|
|
The large open facades has made UNIPORTAL, the adaptable PERI table system, ideal for the 7.7 ft (2.29 m) cantilevered slab edges of this job.
|
|
For this project, PERI Formwork Systems supplied over 65,000 ft² (6,000 m²) of SKYDECK slab formwork system.
|
|
The Concord Cityplace project has significantly contributed to downtown Toronto’s Skyline, adding a total of 20 new towers at the heart of the city, along Lake Ontario.
|